News of 2024
Receipt of Order from Yokohama City for "Work on the 5-Train Water Treatment Equipment at the Kanazawa Wastewater Treatment Center"
Overview of construction
1. Construction name
Work on the 5-Train Water Treatment Equipment at the Kanazawa Wastewater Treatment Center
2. Contractee
Yokohama City
3. Contract date
February 28, 2024
4. Tendering method
Open tendering (general evaluation system)
5. Location
1-17 Sachiura, Kanazawa-ku, Yokohama City, Kanagawa Prefecture
6. Contract amount
2,399,100,000 yen (including tax)
7. Contractor
METAWATER Co., Ltd.
8. Business overview
Work for water treatment equipment
?Sludge collector production and installation [eight ponds]
?Membrane panel-type air diffuser production and installation [two ponds]
?Mechanical stirring machine production and installation [16 units]
?Screw-type spiral pump production and installation [10 units]
?Spiral diagonal flow pump production and installation [four units]), etc
9. Project period
From February 28, 2024, to May 29, 2026