December 28, 2023

Contract Signed for Shunan City Tokuyama Central Purification Center Reconstruction Project - Reconstruction of decarbonization-oriented water treatment facilities -

A corporate group of which METAWATER Co., Ltd. (President and Representative Director: Kenji Yamaguchi; Headquarters: Chiyoda-ku, Tokyo) is the representative company has entered into a consignment contract with Shunan City Water and Sewer Bureau (Water and wastewater business manager: Mamoru Izutsu) for the "Shunan City Tokuyama Central Purification Center Reconstruction Project".

The project will be implemented under the DBO (Design-Build-Operate) method*, which integrates the renewal of the water treatment facilities at the purification center, which have been in service for more than 50 years, with the operation and maintenance of each facility, including the existing facilities. The "Toda-Metawater-Chuken-Quest-Sanyo Fuji-Original Specified Construction Joint Venture" will be responsible for the design and construction work, while "Shunan Water Service Co., Ltd. (special purpose company)" will be responsible for operation and maintenance.

The basic concept of this project is to ensure business continuity through stable and continuous treatment of sewage, reduction of life cycle costs, and development of facilities consider long-term operation and maintenance.

As the representative company, METAWATER will seek to ensure business continuity by combining the city's expertise in sewage works operations with the latest technology from the private sector, while leveraging our experience in public-private partnership projects.

*DBO method: Comprehensive consignment of design, build, and operation to private companies.

周南市.png

1. Overview of project

1) Project name

Shunan City Tokuyama Central Purification Center Reconstruction Project

2) Project location

Tokuyama Central Purification Center 3-1 Harumicho, Shunan City

Eguchi Pump Station 1-1-23 Eguchi, Shunan City

3) Contract amount

19,136,188,274 yen (including tax)

Design and construction: 12,195,469,000 yen (including tax)

Operation and maintenance (O&M): 6,940,719,274 yen (including tax)

4) Project method

Design, Build and Operate (DBO)

5) Project period

Design and construction: December 2023 to September 2031 (approximately 8 years)

Maintenance and operation: October 2024 to March 2050 (approximately 26 years)

6) Facilities in scope and business content

Facilities in scope

*Renovation or renewal of existing facilities is not in scope.

Business content

Reconstruction

Removal only

O&M

Tokuyama Central Purification Center

Facilities to be reconstructed

Water treatment facilities

-

Administration building, supervisory control room

-

Facilities to be removed

Previous sludge treatment facilities

-

-

Existing facilities

New sludge treatment facilities

-

-

Grit chamber, combined sewer improvement facility, mechanical thickening building, and other existing facilities

-

-

Eguchi Pump Station

Existing facilities

Complete set

-

-

Facilities in scope
*Renovation or renewal of existing facilities is not in scope
Business content
Reconstruction Removal only 翱&补尘辫;惭     
Tokuyama
Central
Purification
Center
Facilities to be
reconstructed
Water treatment facilities -
Administration building,
supervisory control room
-
Facilities to be
removed
Previous sludge treatment facilities - -
Existing
facilities
New sludge treatment facilities - -
Grit chamber, combined sewer
improvement facility, mechanical
thickening building, and other
existing facilities
- -
Eguchi
Pump
Station
Existing
facilities
Complete set - -

Facilities in scope

*Renovation or renewal of existing facilities is not in scope.

Business content

Reconstruction

Removal only

O&M

Tokuyama Central Purification Center

Facilities to be reconstructed

Water treatment facilities

-

Administration building, supervisory control room

-

Facilities to be removed

Previous sludge treatment facilities

-

-

Existing facilities

New sludge treatment facilities

-

-

Grit chamber, combined sewer improvement facility, mechanical thickening building, and other existing facilities

-

-

Eguchi Pump Station

Existing facilities

Complete set

-

-

2. Features of business

? Introduction of water treatment facilities that contribute to future decarbonization

? Tracking future fluctuations in water quantity and quality by combining new technologies

? Establishment of an integrated regional cooperative scheme from construction to operation and maintenance

3. Participating companies and their roles

METAWATER Co., Ltd. (Representative company, construction, maintenance, and point repair of mechanical and electrical equipment)

Toda Corporation (Civil engineering and building construction, maintenance and point repair services)

ORIGINAL ENGINEERING CONSULTANTS Co., Ltd. (Design services)

Chuken Co., Ltd. (Civil engineering and construction, maintenance and point repair services)

Quest Co., Ltd. (Construction, maintenance, and point repair of mechanical equipment)

SANYO FUJI DENGYO CO. LTD. (Construction, maintenance, and point repair of electric equipment)

METAWATER SERVICE Co., Ltd. (Operation and maintenance)

4. Overview of SPC (Special Purpose Company)

1) Company name

Shunan Water Service Co., Ltd.

2) Established

November 20, 2023

3) Location

Shunan City, Yamaguchi Prefecture

4) Representative

Shinji Nakabayashi (METAWATER Co., Ltd.), President and Representative Director

5) Capital

20,000,000 yen