News Release
October 12, 2023

Receipt of Order from Chigasaki City for a Project Involving the Provision and Operation of a Treatment Facility for Bulky Refuse at Chigasaki City's Environment Business Center

The corporate group of which METAWATER Co., Ltd. (President and Representative Director: Kenji Yamaguchi; Headquarters: Chiyoda-ku, Tokyo; "METAWATER") serves as the representative company, has received an order from Chigasaki City for a project involving the provision and operation of a treatment facility for bulky refuse at Chigasaki City's Environment Business Center.

This project involves the provision of a new facility required as a result of the deterioration of a bulky refuse treatment facility owned by Chigasaki City. The project entails the provision of a bulky refuse facility (with a capacity of 27 t/5 h) and the operation of that facility for a period of 20 years. The project is to be undertaken via the Design, Build and Operate Method*.

METAWATER is looking to continue efforts aimed at addressing the broad needs of society by leveraging the expertise which it has cultivated when it comes to the construction, operation, maintenance, and inspection of water and sewage works and refuse treatment facilities. In doing so, METAWATER will be contributing to the building of a recycling-oriented society.

*Design, Build and Operate Method: A method wherein an order is issued for a full package which encompasses the Design, Building and Operation phases of a facility.

Overview of construction

1. Construction name

Project Involving the Provision and Operation of a Treatment Facility for Bulky Refuse at Chigasaki City's Environment Business Center

2. Location

836 Hagisono, Chigasaki City, Kanagawa Prefecture, Japan (inside the Chigasaki City Environment Business Center)

3. Order recipient

Representative company: METAWATER Co., Ltd.

Constituent member: Kamei Kogyo.Co.,Ltd.

Partners: Daisho Kensetsu Co., Ltd., Satoh Co., Ltd.

4. Project period

Construction period: September 2023 to March 2026

Operation period: April 2026 to March 2046

5. Contract amount

11,115,500,000 yen (including tax)

6. Project method

Design, Build and Operate Method

7. Facility overview

Treatment methods: Fragmentation, sorting, and storage

Facility scale: Large refuse and non-combustible refuse (capacity of 27 t/5 h)

8. Overview of tasks

Design and construction: Design and construction of a new facility

Operation, maintenance and inspection: Operation of new facilities, reception and measurements (including measurements for the existing measurement building), operational control, inspections, tests, repairs, rehabilitation, utilities management, etc.