Receipt of Order from the Tokyo Metropolitan Government for the "Reconstruction of the Sludge Incineration Electric Equipment at the Nanbu Sludge Treatment Plant, Part 3"

Overview of construction

1. Construction name

Reconstruction of the Sludge Incineration Electric Equipment at the Nanbu Sludge Treatment Plant, Part 3

2. Contractee

Bureau of Waterworks Tokyo Metropolitan Government

3. Contract date

September 28, 2022

4. Tendering method

Open tendering

5. Location

5-2-1 Jonanjima, Ota-ku, Tokyo (inside the Nanbu Sludge Treatment Plant)

6. Contract amount

1,991,000,000 yen (including tax)

7. Contractor

METAWATER Co., Ltd.

8. Business overview

Power distribution panel, full set
High voltage transforming equipment, full set
Monitoring and control equipment, full set
Uninterruptible power supply equipment, full set
Instrumentation equipment, full set
Wiring work, full set

9. Project period

580 days from September 29, 2022