Overview of construction
1. Construction name
Yamato City Chubu Purification Center sludge treatment facility construction work Part 4
2. Contractee
Japan Sewage Works Agency
3. Contract date
March 22, 2021
4. Tendering method
Comprehensive evaluation open tendering
5. Location
Within Fukami, Yamato City, Kanagawa Prefecture
6. Contract amount
1,397,000,000 yen (including tax)
7. Contractor
METAWATER Co., Ltd.
8. Business overview
Sludge thickening equipment¡¡¡¡Full set
Chemical feeding and dehydrator equipment¡¡¡¡Full set
Deodorization equipment¡¡¡¡Full set
Other auxiliary equipment¡¡¡¡Full set
9. Project period
March 23, 2021 to March 31, 2022