Receipt of Order for "Kyoto City: High Speed Filtration System Machinery and Combined Primary Sedimentation Tank Machinery Development Projects in Fushimi Water Environment Conservation Center"
Overview of High Speed Filtration System Machinery Development Project
1. Construction name
High Speed Filtration System Machinery Development Project in Fushimi Water Environment Conservation Center
2. Contractee
Kyoto City Waterworks Bureau
3. Contract date
September 16, 2016
4. Tendering method
Open tendering
5. Location
Yokooji Senryomatsu-cho, Fushimi-ku, Kyoto City
6. Contract amount
1,100 million yen (excluding tax)
7. Contractor
METAWATER Co., Ltd.
8. Overview of construction
A set of high speed filtration system equipment (water treatment capacity: 165,800m3/day), two high speed filtration system inflow gates, three washing wastewater pumps, one low concentration deodorizer, a set of plumbing valves
9. Project period
September 17, 2016 to March 30, 2018
Overview of Combined Primary Sedimentation Tank Machinery Development Project
1. Construction name
Combined Primary Sedimentation Tank Machinery Development Project in Fushimi Water Environment Conservation Center
2. Contractee
Kyoto City Waterworks Bureau
3. Contract date
September 21, 2016
4. Tendering method
Open tendering
5. Location
Yokooji Senryomatsu-cho, Fushimi-ku, Kyoto City
6. Contract amount
820 million yen (excluding tax)
7. Contractor
METAWATER Co., Ltd.
8. Overview of construction
Four primary sludge collectors, two primary sludge pumps, eight primary scum collectors, one scum separator, one deodorizer, a set of plumbing valves
9. Project period
September 22, 2016 to March 30, 2018